#Post#: 127761--------------------------------------------------
Re: Bus lane PCN Southwark Council
DIR By: ILoveCats123
Date: August 13, 2026, 4:29 pm
---------------------------------------------------------
Okay we’ll submit reps without mentioning the delay in serving
the EN.
Once we can figure it out, we can deal with that part at LT.
Sound good?
#Post#: 127763--------------------------------------------------
Re: Bus lane PCN Southwark Council
DIR By: fraser.mitchell
Date: August 13, 2026, 5:14 pm
---------------------------------------------------------
--- Quote from: Hippocrates link ---
>
> [quote author=Incandescent link=topic=9128.msg127742#msg127742
date=1786644264]
> The CHief Adjudicator has made it clear to councils that
delays of over 3 months to do anything in the enforcement
process is grounds for cancellation, unless very good reasons
are submitted.
>
--- End Quote ---
Where please?
[/quote]
I read about this somewhere some time ago, and was quite sure
it is fact, but it is not in the Practice Directions, so can
only assume it is in private correspondence from Mr Chan. I
believe it is in an adjudication somewhere as a fairness issue.
Sorry cannot be more definite. Maybe Ivan knows more. However,
there is a case in the Key Cases listing where delay is
explored. This is under the old 1991 legislation. The case here
is 1998 when it was PATAS
HTML https://www.londontribunals.gov.uk/sites/default/files/keycases/Davis41.pdf
#Post#: 127765--------------------------------------------------
Re: Bus lane PCN Southwark Council
DIR By: fraser.mitchell
Date: August 13, 2026, 5:26 pm
---------------------------------------------------------
I continued to dig around and things like this tend to be
buried, but in the process for Bus Lane PCNs, it is stated that
councils should normally respond to reps against an EN within
three months.
I confess that there is no stricture against service of the EN
itself.
HTML https://www.londontribunals.gov.uk/eat/understanding-enforcement-process/bus-lane-pcn-enforcement-process#en
However, it is clear that delays in enforcement is an issue that
has been around since the 90s. Would a London Tribunals
adjudicator be happy if the EN was served a year later ? Surely
not.
#Post#: 127768--------------------------------------------------
Re: Bus lane PCN Southwark Council
DIR By: Hippocrates
Date: August 13, 2026, 6:21 pm
---------------------------------------------------------
--- Quote from: Incandescent link ---
>
> I continued to dig around and things like this tend to be
buried, but in the process for Bus Lane PCNs, it is stated that
councils should normally respond to reps against an EN within
three months.
> I confess that there is no stricture against service of the EN
itself.
>
>
HTML https://www.londontribunals.gov.uk/eat/understanding-enforcement-process/bus-lane-pcn-enforcement-process#en
>
> However, it is clear that delays in enforcement is an issue
that has been around since the 90s. Would a London Tribunals
adjudicator be happy if the EN was served a year later ? Surely
not.
>
--- End Quote ---
We can raise this later. Just got back from the visit to the
local as too hot to go out during the day. Quite close to the
infamous YBJ in Kingston Road. ;D
#Post#: 127787--------------------------------------------------
Re: Bus lane PCN Southwark Council
DIR By: Hippocrates
Date: August 14, 2026, 7:10 am
---------------------------------------------------------
The issue is further compounded by the fact that the law does
not even state that an informal challenge needs to be considered
but nearly all councils in London do.
*****************************************************