The construction of the President Néstor Kirchner gas pipeline
is the flagship of a public policy to expand the transportation
network called Sistema Transport.Ar . Stage i between Tratayén
(Neuquén province) and Salliqueló (Buenos Aires province) is
carried out under a public works scheme, directed by the state
company Energía Argentina sa (Enarsa) and executed by private
contractors. What is remarkable has been its realization in
pressing deadlines, with the purpose of arriving by the winter
of 2023 with import substitution (which will happen from the end
of July.
The Ministry of Energy has maintained that it is a true "feat",
since it was done in record time India Email List
HTML https://dbtodata.com/india-email-data/
a technical point of view
(10 months, which usually takes 24), with an average welding of
five kilometers of pipe per day.43. The construction companies
also speak of a "feat": a 583-kilometer pipeline that involved
the directed crossing of the Colorado River between Río Negro
and La Pampa; employed more than 10,000 skilled workers (more
than four million man-hours), including welders with
state-of-the-art technology on a global scale, implemented for
the first time in the country: double joint plants, automatic
welding systems (operated by 45 specialized technicians from
Turkey who welded more than 100 joints per day from inside and
outside), more than 9,000 trips by truck of the pipes that
totaled an accumulated of six million kilometers.
HTML https://zh-cn.indiaphonelist.com/wp-content/uploads/2023/04/image_2023_08_29T07_29_31_891Z-300x182.png
HTML https://dbtodata.com/india-email-data/
In addition, more than 1,400 national pieces of equipment were
used, including sideboom trucks , pipe welders), motor graders,
bulldozers, excavators, pipelayer cranes and tractors. It is a
work whose repayment does not exceed two years, during which it
will save a total of 4,400 million dollars. Thus, in the medium
term (and together with crude oil exports), the energy trade
balance will go from a deficit in 2022 of 5,000 million dollars
to be positive in 2025, with income projections of 18,000/20,000
million to 2030. Then , stage ii of the President.
*****************************************************