#Post#: 215--------------------------------------------------
Final Determination made on SEQR and the Erie Canal Earthen
Embankment Remediation Project
DIR By: Doug K
Date: December 20, 2018, 8:28 pm
---------------------------------------------------------
More good news for the Erie Canal.. it's Breathe of Life.
HTML https://www.dec.ny.gov/enb/20181031_not8.html
The final determination from the DEC, regarding the "SEQR angle"
that some have used in an attempt to stop the EERP Safety
project has been made. The work being done IS repair of an
existing Flood Control Structure, just like NYPA & the NY Canal
Corp have said all along. Again, when science is behind you it's
just a matter of time before the truth wins out.
This means the EERP Phase 1 work from Rochester EAST through
Brighton, Pittsford, & Fairport WILL continue at some point in
the near future. Most likely put them at least a year behind the
rest of this Overall Section but at least those living in
potential Flood Hazard Zones will start to get the safer
Embankment Dams they need. EERP Phase 2 work on the westside is
rolling along very well, check more posts in the ECNA Forum for
more
[attachimg=1]
*****************************************************